Blog

Way In Building & Civil Construction

A time impact analysis (TIA) is a method used to determine the extent of the impact of potential delays in the construction process. This process can be a preferred way to promote negotiation and later agreements on delay claims. Such an assessment is done using existing schedules, analyzed with all related input entered into the schedule to demonstrate the reason or possible effects on the schedule.​

Time impact analysis is usually performed by a project scheduler and can be used on the vast majority of construction projects. This method involves the insertion or addition of activities indicating delays or changes in a schedule representing progress up to the point when a delay event occurred. That allows for an assessment of the impact of those activities.

 

Expectations

A time impact analysis will be applied to forecast the construction process and analyze what is going on and what the outcome will be. It requires a critical path method schedule (CPM schedule) that can show the differences between a schedule that does not include a delay and one that does include an activity modeling a delay. A time impact analysis is required to calculate with a standard method, the results of the actual project delay.

The analysis is not the project reality simulation. It is intended to understand the time impact caused by a single event or series of events and how they will impact the project schedule. It is a useful tool for projects that are currently ongoing and will present a real-time idea of how the contract adjustment is required.

The final result of the time impact analysis must be presented shortly after completion to the contractor. Otherwise, he might present an additional time extension claim of constructive acceleration. It is the best technique for determining the amount of extension of time that the contractor should have been granted at the time that an excusable risk occurred.

 

Uses for the Method

Time impact analyses are used on these occasions:

  1. When the contractor has not been able to provide remediation instructions, and it is not able to redeploy his workforce.
  2. If there are actually delays in events that are undergoing construction activities.
  3. When delays are already being expected due to external or internal circumstances.
  4. If there is a need to model delays in short or simple construction activities. If delays are longer than usual, additional methods and tools must be used in conjunction with the TIA.

 

When to Try a Different Approach

The time impact analysis should not be used or will not present the best results when:

  1. Your actual project schedules have not been updated. TIA will not present a real outcome when data input on the analysis has not been updated with real data from the construction activities.
  2. Work plans based upon resource considerations could be easily adjusted without creating a detriment to the project completion.
  3. Mitigation work has already been started. If the constructions schedule has been altered, the less effective the modeling of the delay will be.

 

The Procedure to Follow

A time impact analysis requires the following steps:

  1. The delay should be described as simply as possible with the fewest number of activities reflecting the project delay.
  2. Select the schedule to impact. The schedule should be the latest updated schedule for the project.
  3. Add the impact activities and make the necessary adjustments to the project schedule.
  4. Recompute the CPM and note a change in the project completion date.
  5. Determine the amount of project delay.
  6. Determine the actual dates of the delay using the original schedule

 

Your Final Checklist

When performing a time impact analysis, be sure to:

  1. Study and understand the scope of the directed change or analyze the extent of the delay.
  2. Analyze all contract documents, field directions, contract clauses, drawings, orders, specifications, and conditions that could exert any kind of influence on the expected delay.
  3. Identify and describe the condition encountered before performing the time impact analysis.
  4. Identify all related construction activities that are or could be affected by the expected delay.
  5. After a complete analysis of the construction schedule, determine all related dates — start, duration, and finish — for all affected activities.
  1. Prepare a complete set of documents that define when the delay started and what actions took place at that moment, and demonstrate the effects of the delay on the updated schedule and how the remaining activities should be altered, if required, to complete the project on time.
  2. Highlight extraordinary measures required to bring the project back on schedule.
  3. Check that actual delays are a result of the changed directives, not from a nonexcusable cause.
Contractor shaking hands with an engineer before he ask for a time extension on the construction contract.

When and How to Request a Time Extension on a Construction Project

  • Digger and truck working in quarry

No Comments

  1. Hi, this is a comment.
    To get started with moderating, editing, and deleting comments, please visit the Comments screen in the dashboard.
    Commenter avatars come from Gravatar.

      • Ho Ngoc
      • July 22, 2017 at 08:51 am

      Integer sollicitudin ligula non enim sodales, non lacinia nunc ornare com
      are risus in euismod varius nullam feugiat ultrices.

    • Ho Ngoc
    • July 22, 2017 at 08:51 am

    Integer sollicitudin ligula non enim sodales, non lacinia nunc ornare. Sewid commodo
    are risus in euismod varius nullam feugiat ultrices. Sed condimentum est libero

    • Ho Ngoc
    • July 22, 2017 at 08:51 am

    Integer sollicitudin ligula non enim sodales, non lacinia nunc ornare com
    are risus in euismod varius nullam feugiat ultrices.

Leave a Reply to Ho Ngoc Cancel reply

Your email address will not be published. Required fields are marked *